We constructed a Ferry goods ramp for the entry of consumable goods into Gibraltar.

The work involved breaking out an existing MOD culvert containing many services including a redundant fuel line, re-diverting/removing services, installation of 50-ton mooring bollards, a heavily reinforced concrete ramp and new offices for Customs with road barrier.

Extremely difficult works due to the location on the quay side.

 

Photo 07-10-2019, 11 46 59 Photo 07-10-2019, 11 47 12 Photo 07-10-2019, 11 48 01 IMG_4487 IMG_4486 IMG_4484