To facilitate the demolition of the North Mole warehouses to make way for the new Generating Station, we were employed to design & build a new warehouse on a brown field site to accommodate 2No. companies, GFI & Toyota Gibraltar Stockholdings (TGS).  The total floor area is approx. 1500m2, and the frame is 13.50m at the apex. The building was split into two units to for each of the companies. The construction is a steel portal frame with aluminium twin-skin cladding to the roof and walls. Due to the nature of the businesses all internal walls are blockwork, and the floors a Holorib with concrete slab infill.  The works were programmed for completion in 160 days, and despite it’s location on the North Mole, the various stoppages for Ocean Cruise dockings, the project was completed on time, and in budget.